The problem with estimates and dates in software is simple: nearly everyone wants them, and having target dates usually makes things worse. Worse! Are there exceptions? Yes – but not many!
I’ve written agonizingly loooooong papers on this subject. But this is just a blog, so here is a bite-size thought to chew on.
Software estimates of dates might be a good thing if the thing we were estimating were something we have done over and over again, and had reasonable standards to apply. But we don’t.
Think of things like your commute to work, and the commutes of other people to the same place. Say you tell a friend your commute this morning took half an hour. Your friend will immediately be able to react to that information by saying, “whoa, was there an accident?” or “how come they didn’t catch you, lead-foot?” Your friend has a clear idea of the range of reasonable times for a “normal” commute, and can use that knowledge to judge on his own whether the one this morning was fast or slow, and by a lot or a little.
Now suppose a friend tells you that he's just finished designing a database, and that it took a week. Lots of people have designed databases. Say you’ve designed lots on your own. How do you respond? Is your friend a superman, for designing the database in record time, or a slug? The fact is, without knowing a whole lot about the details of the database to be designed, you have no idea. Even if your friend tells you some basics like the number of tables and columns, you still really have no idea. Was there a starting model? Are there special performance, size, interface or compatibility requirements? Were there a bunch of conflicting interests to account for? Depending on lots of details like these, even knowing the “raw” size of the database schema that was designed, you still have no way of judging.
Lots of interesting things come from this observation. One of them was taken up and exploited by the big services firms long ago. Here it is: the people who look at your project plan typically don’t have a clue – not even a foggy idea – of whether the times and resources assigned are reasonable. What the manager typically wants is confidence that, whatever resource and time commitments may be made, they are kept. So project management, in this context, is all about having lots and lots of highly technical looking stuff with charts and diagrams and fancy reports to justify what are – all too often -- completely outrageous resource and time commitments. No one looking at them has any way of knowing that they’re outrageous. So they get approved. The expectations are eventually met. And everyone’s a hero!
Speed vs. Predictability on the Race Track
Imagine we’re on a race track and there are some people running the 100 meter. Most of the people are outstanding runners, so they’re always competing with each other. In every race, all but one of them is a loser, and they tend to set aggressive goals of the times they’re going to make, which they frequently miss by a little.
The typical project manager would look at them as a bunch of unpredictable losers! They usually miss their goals, after all, and they practically always lose the contest they enter!
Now someone sidles up to the disappointed project man and says that he’s a different breed. “When I say I’m going to do something, I do it” is the line. So our runner says, see that 100 meter track over there? I’m going to go up to it within the next 15 minutes, and I’m going to tell you when I’m starting. You time me. I’m going to cross the finish line with 60 seconds. And I’m going to try to exceed your expectations.
Naturally, the project man is impressed. This is what he’s been looking for, a winner who does what he says he’s going to do.
Ten minutes later, the guy goes to the starting line, announces his start, and 55 seconds or so later, crosses the finish line, ahead of schedule! Wow! He started ahead of time and took even less time than he told me – this guy is a star!
Speed or Predictability: You Choose
What this boils down to is that you’ve got a choice. Which do you want: speed or predictability?
If you want predictability, dates are your friend. By all means, set a 60 second target for the hundred meter dash, and consistently beat your estimate. You’ll look like a hero to the ignorant, and you’ll do your part in flushing your business down the toilet.
If on the other hand you want speed, you will avoid setting date targets like the evil, mutilating plague they are. You will clearly define the target a hundred meters from here, and encourage your swift runners to start before the words get out of your mouth, and arrive yesterday. You may cause a bit of confusion among business people to whom this way of working seems strange and new, but they’ll quickly adapt as they see high spirits, pride of accomplishment … and results, the like of which they’ve never seen before.